Equinox Gold claims progress on construction of its Greenstone open-pit gold mine is on budget and on schedule to pour its first gold bar sometime in the first half of 2024.
The Vancouver gold company delivered an update on July 27 on the pace of progress of its Greenstone pit project, three kilometres south of Geraldton.
The overall project is 35 per cent complete with US$315 million (26 per cent) of its $1.23-billion construction budget spent as of June 30.